Project Timeline (Tentative) Banner

Project Timeline (Tentative)

Demolition of Quarters > Decanting > Construction of In-patient Extension Block > Planning for Stage 2 Redevelopment

2018 - Demolish Staff Quarters Block C, E and Lecture Theatre Building
- Construction of the decanting building at Shatin Hospital start
2019 - Demolish Staff Quarters Block A and D
- Groundwork for the new In-patient Extension Block start
2020 - The decanting building at Shatin Hospital open for the relocation of the user departments of the quarter blocks
2021 - Core construction works for the new In-patient Extension Block start
2025-2026 - Core construction works for the In-patient Extension Block finish
- Renovation of the Main Clinical Block and Trauma Centre begin
2027 - PWH Phase II Redevelopment Project (Stage 1) complete
- Planning for Stage 2 (i.e. Ambulatory Care Centre and Cancer Centre) begin

Updated on 15 May 2018
@