Construction Progress

What's New




12.2024

最新動態10

The North District Community Health Centre (NDCHC) commenced the general out-patient service on 16 December. Patients receiving regular follow-ups at the Shek Wu Hui Jockey Club General Out-patient Clinic have been transferred to the NDCHC to continue their service.

On December 9, the center invited the North District Officer, North District Council members, and the North District Caring Teams for a tour of the facilities. The new clinic offers significantly more space compared to the Shek Wu Hui Jockey Club General Out-patient Clinic, along with enhanced services and facilities. It integrates a wide range of one-stop electronic services to improve the patient experience. Key features include a Smart Pharmacy, Auto Dispensing Machine, Augmented Reality rehabilitation training, etc.

We look forward to the gradual rollout of services at the NDCHC building, which is expected to further elevate the standard of healthcare in the district and provide residents with a more convenient and innovative smart healthcare experience.



07.2024

最新動態10
最新動態10

The construction works of North District Community Health Centre Building has been completed. Starting from May, various departments including the Family Medicine Department of the New Territories East Cluster, Allied Health Departments of North District Hospital had been arranged to enter the building and conduct inspections on their respective floors. They had also communicated the necessary defeat rectifications to the Architectural Services Department (ArchSD) and the contractor. ArchSD will finish the rectifications and hand over the building to the Hospital Authority (HA), Department of Health, and Social Welfare Department by late July tentatively. The HA will then arrange service relocation and move-in for service commencement as soon as possible.



03.2024

最新動態8

The construction of the North District Community Health Centre Building is anticipated to be completed as soon as late April 2024 and then handed over to North District Hospital. In light of this, the New Territories East Cluster representatives have provided updates on the works progress and listened to their concerns at the North District Council Meeting, Lung Shan Area Committee Meeting, and Fung Shui Area Committee Meeting in mid-March. Council members and committees members unanimously welcome the completion of the new building and express their concern for the further development of healthcare services in the future. We will continue to closely communicate with various stakeholders in the community to improve the project and live up to the public’s expectation.



02.2024

最新動態8
最新動態8

The construction of the North District Community Health Centre Building has entered its final stage. The contractor has started to dismantle the scaffolding of the building, so that the façade of the building, including window walls, cladding and curtain walls can be clearly seen. In the meantime, the hospital is preparing for the move-in arrangement.



01.2024

最新動態5

The site formation and foundation works of NDH Expansion Project are in full swing. Besides, the main contractor is also installing hoarding graphics that include the vision and mission of Hospital Authority. We understand that the noise and vibration generated by the foundation and piling works have caused inconvenience to colleagues and patients. We would like to express our gratitude to all departments’ understanding and continuous support to the daily operations of the hospital.



12.2023

最新動態5

The construction of the North District Community Health Centre Building is in full swing. As of November 2023, the superstructure has been completed, while the interior fitting-out is still ongoing. It is expected that the project will be completed and handed over to the hospital in April 2024. The hospital is now procuring relevant medical equipment and furniture to match the opening of the building.



11.2023

最新動態5
最新動態5

The construction of the North District Community Health Centre Building is currently underway, and the curtain wall of the building is partially completed. NDH together with Hospital Authority Capital Planning Department and Architectural Services Department had conducted a visit to construction site and checked out the progress of the project. It is expected that the project will be completed in April of 2024.



10.2023

最新動態1

As the 1:50 User Engagement Meetings for NDH Expansion Project are approaching the final stage, Project Consultants are preparing a series of workshops to introduce the sign-off arrangement and tips for reading the drawings. Colleagues are welcome to join the workshops and access the video footage on the intranet of NDH Expansion Project. Please continue to support and provide valuable suggestions to NDH Expansion Project.



09.2023

最新動態1

The Staff Forum for NDH Expansion Project was held on 21 Aug 2023 (Mon). Project Consultants presented the schedule and progress of NDH Expansion Project. Majority of the reprovision works have been completed. Some other preparatory works has been commenced since Aug 2023.



08.2023

最新動態2

We are glad that LegCo Finance Committee of the Legislative Council approved funding of over $30 billion for the main works of the North District Hospital Expansion Project in June 2023, which is the final and most important stage. Meanwhile, a Staff Forum for NDH Expansion Project will be held on 21 August 2023 (Monday). Project Consultants will introduce the progress of the expansion project, the timeline and arrangement of the upcoming works and the relevant monitoring and mitigation measures.



06.2023

最新動態3


As part of the preparatory works of the NDH Expansion Project, the Reprovision of A&E North Wing has been completed. The works include new access to the A&E Department and a new Emergency Medicine Ward on 5/F. The handover between the hospital and the Head Office Capital Planning Department was successfully completed on 1 June. The new A&E Department will commence services soon to help alleviate the overcrowding situation at the existing A&E Department. We understand that the project may cause inconvenience to colleagues and patients and we would like to express our gratitude for your continued support and understanding.